Tashkent, Uzbekistan (UzDaily.com) -- Consortium of the South Korean companies Daewoo and Hyundai completed construction of two combined-cycle gas turbines with capacity of 900 MW at the Talimarjan thermal power plant in Kashkadarya region.
According to Uzbekenergo, two combined-cycle gas turbines with capacity of 900 MW were constructed at the Talimarjan thermal power plant within the investment project. The company said that the plant started to generate electricity.
In March 2013, South Korean Daewoo and Hyundai signed a contract with Uzbekenergo for modernization of Talimarjan thermal power station for US$861 million.
The consortium constructed two 450-megawatt combined cycle power plants in Talimarjan within the project. Mitsubishi Corporation of Japan supplied combined cycle power plants.
The project cost was US$1.28 billion. The Government of Uzbekistan attracted ADB loan for US$350 million and loan of Japan International Cooperation Agency (JICA) for US$300 million, Fund for Reconstruction and Development of Uzbekistan- US$250 million and own resources of Uzbekenergo.
First power block of Talimarjan thermal power station was commissioned in December 2004. The designed capacity of the block is 800 megawatt. The construction cost was US$400 million. Launch of new combined cycle power plants will increase electricity production by 2.3 times – to 10.4 billion KWH a year.
Construction of two new combined cycle power plants will allow to increase production of electricity up to 20.4 billion KWH a year.